  • Inspection Items for the Arrival Acceptance of Variable-Frequency Series Resonant Test Devices at Newly Built Substations

    With the increase of distribution network transformation and new energy grid connection projects, the use scenarios of variable frequency series resonance test devicesare also expanding. Recently, there have been multiple technological renovation projects involving the selection, configuration, and use of variable frequency series resonance test devices. The following is a summary of some experience gained during the project implementation process.


    resonant test system


    1、 Equipment configuration in distribution network renovation project

    The 2025 distribution network renovation project in a certain region involves equipment updates for 12 35kV substations, among which the variable frequency series resonance test device is the main item in the equipment procurement list.

    1. Configuration plan: Based on the equipment types and voltage levels covered by the project, three different specifications of variable frequency series resonance test devices have been selected to meet all testing requirements.

    2. Procurement cycle: The entire procurement process, from the preparation of technical specifications to the acceptance of equipment upon arrival, takes about 45 days.


    2、 Testing requirements for new energy power plants

    The grid connection testing of photovoltaic power plants and wind farms has different requirements for the frequency conversion series resonance test device, and the equipment configuration scheme of traditional power testing needs to be adjusted accordingly.

    1. Photovoltaic power station: Insulation testing of inverters, box transformers, and combiner boxes is a necessary project before grid connection, requiring a variable frequency series resonance test device with measurement capabilities suitable for DC systems.

    2. Wind farm: The testing environment conditions for wind turbine tower foundations and box transformers are poor. It is recommended to choose a higher protection level variable frequency series resonance test device model.


    3、 Feedback on the use of variable frequency series resonance test device in different projects

    We have collected actual usage feedback from several units, and the following issues have repeatedly occurred in multiple projects, which are worth paying attention to in subsequent procurement and usage.

    1. Low temperature start-up issue: When the winter temperature in northern regions drops to minus 15 ℃, the LCD screen response of some variable frequency series resonance test devices slows down. It is recommended to choose a wide temperature screen model.

    2. Outdoor power supply: Some outdoor construction sites do not have mains power, and the battery life of the variable frequency series resonance test device becomes a limiting factor, requiring backup generators or large capacity mobile power sources.


    4、 Collaborative use scheme with lightning protection grounding resistance measuring instrument

    In the comprehensive maintenance project, the frequency conversion series resonance test device needs to work in conjunction with the lightning protection grounding resistance measuring instrument. Reasonable equipment scheduling and personnel arrangement can effectively shorten the maintenance period.

    1. Equipment scheduling: When multiple detection tasks are parallel, it is recommended to group them according to voltage level and equipment type, and each group should be equipped with one variable frequency series resonance test device and one lightning protection grounding resistance measuring instrument.

    2. Data integration: The testing data of each group should be summarized on the same day on a unified platform for the project technical leader to evaluate the overall progress and quality.


    5、 Subsequent maintenance and training arrangements

    After the new equipment is in place, training and daily maintenance are equally important. A sound training system can reduce the risk of human error and extend the service life of equipment.

    1. Operation training: The manufacturer's technical personnel should attend the training for 1 to 2 days, covering the basic operation, safety precautions, and simple troubleshooting of the variable frequency series resonance test device.

    2. Ledger management: Establish an equipment ledger for the variable frequency series resonance test device, recording equipment numbers, purchase dates, calibration records, and maintenance history.


    FAQ

    Q1: Can the same frequency conversion series resonance test device be used for new energy grid connection detection and traditional power detection?

    A1: It is necessary to confirm whether the AC/DC measurement range of the equipment covers the parameter requirements of the new energy system, and some scenarios may require additional configuration of adapters.

    Q2: What approval procedures are required for the procurement of variable frequency series resonance test devices in technical renovation projects?

    A2: Generally, the technical department needs to propose requirements, the biotechnology department reviews technical parameters, the material department organizes procurement, and major projects also require approval from company leaders.

    Q3: Who should I contact if there are still any issues after the equipment training?

    A3: First, consult the operation manual and common problem document. If you cannot solve the problem, you can contact the manufacturer's technical support hotline. Wuhan UHV provides lifelong technical services.

    You Might Also Like

    • Have Any Questions!

      DON'T HESITATE TO CONTACT US ANY TIME
      Contact us
    • Visit Us

      Building 6, Optics Valley Optical-Mechanical Industrial Park, 84 Gaoxin 5 Road,
      East Lake New Technology Development Zone, Wuhan City, Hubei Province, China

    • Email Us

      qiao@hvtest.cc

    • Call Us

      +86-15871365102